Circular Line Resumes and Replacement Buses Withdrawn
Madrid’s Regional Department of Transport has confirmed that after nine months of modernization work, Madrid Metro Line 6 (L6) will fully resume normal operations on December 20, 2025 (this Saturday). At that time, the section between Legazpi and Moncloa, closed since September of this year, will reopen to the public, marking the complete restoration of the circular service.
With the resumption of metro services, the replacement buses operated by Madrid’s Municipal Transport Company (EMT) will complete their mission. According to the approval from the municipal government’s executive committee, these alternative routes will be phased out between this Thursday and December 23, with passengers returning to the underground metro system.
Modernization Project for Increased Speed and Efficiency
This large-scale renovation aimed to enhance operational efficiency by automating the line and upgrading its infrastructure. The project was divided into two phases: the first, completed between March and August, involved 11 stations between Méndez Álvaro and Moncloa; the second phase began on September 6, closing 17 stations on the eastern part of the circular line for construction.
To minimize the construction period, teams worked 24 hours a day, 7 days a week. This efficient approach ultimately allowed the line to reopen 11 days ahead of schedule. Over the past seven months, engineers have dismantled old tracks, replaced a total of 86,057 meters of rails, and installed new concrete track slabs. These improvements will increase train speeds by 27% and significantly boost the line’s passenger capacity.
Next Phase: Platform Door Installation and Nightly Closures

Although the circular line has resumed normal operation, the modernization of Line 6 is not yet complete. The next major phase will be the installation of platform screen doors across the entire line. In preparation for this, 3,990 reinforcement pillars and 7,700 meters of temporary walkways were installed during the previous works, laying the foundation for subsequent construction.
To accommodate the installation of the platform doors, the operating hours of Metro Line 6 will be adjusted starting from January. During the construction period (expected to last throughout 2026), the line’s night service from Sunday to Thursday will end early at 23:00. To address this adjustment, the EMT circular bus service will be reactivated on the nights of January 7 and 8 to ensure public transport is available for residents after 23:00.