Legislation Before Location: Spain Learns from Past Mistakes
Facing the ultimate disposal of nuclear waste, the Spanish government is adopting a more cautious new strategy. According to the newly approved General Radioactive Waste Plan (PGRR), a specific law will first be enacted to regulate the entire site selection process before any search for a concrete location begins. This move aims to learn from historical lessons—site selection attempts in the 1990s and the temporary storage facility project in Villar de Cañas, Cuenca, both failed due to strong social opposition and political maneuvering.
The new law is expected to be completed by 2028, with its core principle being the establishment of a transparent, fair, and socially consensual site selection mechanism. Enresa, the state-owned company in charge of the project, has already completed the first phase of technical assessments and will submit its report to the Ministry for Ecological Transition to provide technical support for the subsequent legislation.
Official Timeline vs. Industry Demands
According to the official plan, the timeline for this monumental project spans half a century. Spain’s existing nuclear power plants will be progressively phased out between 2027 and 2035, and the nuclear waste they generate will first be stored temporarily at each plant site for 50 years.
The official construction timeline for the Permanent Geological Repository (known as AGP in Spanish) is as follows:
- 2029-2032: Initial screening of candidate sites nationwide.
- 2033-2039: In-depth studies and determination of the final site.
- 2040-2059: Detailed geological surveys and site characterization.
- 2060-2071: Facility construction and implementation phase.
- 2073: Official commencement of operations.
However, energy giants including Endesa, Iberdrola, and Naturgy hope to significantly accelerate the process, proposing to advance the completion date by 25 years to 2050. Their main motivation is to remove the nuclear waste from the decommissioned plant sites as soon as possible, in order to repurpose the land for new industrial development projects.
Future Challenges and Social Impact
Although the government remains open to accelerating the plan, the core challenge of the project remains site selection. An ideal location requires stable geological formations of clay, granite, or salt rock. However, it is foreseeable that any area listed as a candidate will likely face strong opposition from local residents.
The national debate on “where the nuclear waste goes” has just begun. It not only concerns Spain’s energy future and environmental security but will also profoundly impact the potentially selected regions for decades to come. How to strike a balance between national needs and local interests will be a major test for the Spanish government.