Project Completed But No Occupancy Permit
The ALMA residential complex in Estepona, a renowned coastal city in southern Spain, was fully completed in mid-2025. However, due to the failure to connect the crucial electricity supply, the project has so far been unable to obtain the First Occupancy License (Licencia de Primera Ocupación) from the government. This means that the 72 families who have already paid for their properties, despite having the keys, cannot legally move in. This move-in impasse has lasted for over seven months, leaving the owners extremely anxious.
Bureaucratic Impasse and Blame Game
The root of the problem lies in complex administrative procedures and the shifting of blame among various parties. The power supplier, Endesa, pointed out that although the Estepona City Council initiated an electricity reservation process for the project back in 2021, the application was never formally processed because the complete technical documentation was not submitted. It wasn’t until December 2025 that the City Council resubmitted the application, but by then, the local power grid’s capacity was already saturated and unable to immediately meet the new demand. Endesa stated that it must process applications in the order they are received and cannot provide priority connection for this complex.
Meanwhile, the homeowners believe that the city council’s errors, the developer’s inadequate planning, and the power company’s rigid procedures have collectively led to the current predicament. The developer even offered the owners the choice to “give up the purchase or accept the property without a legal permit,” a proposal that has sparked strong dissatisfaction among the homeowners.
Homeowners Trapped in Double Financial Pressure
For these affected families, the delay has brought a heavy financial and emotional burden. Some owners had already sold their original homes to buy the new property and are now forced to live with relatives. Other families face the dilemma of paying rent on their current homes or mortgage payments on the new, vacant property while being unable to move in, leaving them in a difficult situation.
Residents Plan Protests and Demand Solutions
Faced with an indefinite wait, the affected families have united and announced plans to hold a protest on January 16, 2026, demanding that all parties take responsibility and resolve the issue immediately. They are calling on Endesa to fulfill its duty to supply power and urging the city council to expedite coordination and issue the First Occupancy Licenses as soon as possible. The owners have stated that if the problem is not resolved, they do not rule out escalating their protests to Málaga and even the capital, Madrid.
Currently, the Estepona City Council has written to the Spanish Ministry for the Ecological Transition, acknowledging that the national power grid is under pressure to meet the demands of the rapidly growing population in the coastal region. They have requested intervention from higher authorities to mediate and alleviate the power shortage crisis for new development projects.