Japanese firm Eurus Energy has announced that its A Ruña II wind farm in Spain has commenced commercial operation. The project has a capacity of 21 MW, is located in the Galicia region, and consists of seven 3 MW wind turbines. With this commissioning, the company’s total installed wind power capacity in Spain has reached 574 MW.
Project Commissioning Details
The A Ruña II wind farm has a total installed capacity of 21 MW, composed of seven wind turbine generators, each with a capacity of 3 MW. The project is located in the municipalities of Mazaricos and Dumbría in the autonomous community of Galicia, Spain. The wind farm began operations in January 2026.
Technical Specifications
The wind turbines for the project were supplied by Vestas Wind Systems. Each turbine has a capacity of 3 MW, with the seven units collectively forming the 21 MW total capacity. The local company Elecnor was involved in related project work.
Company Capacity Update
Following the commissioning of A Ruña II, Eurus Energy’s total installed wind power capacity in Spain now stands at 574 MW. The company already had several wind power projects in Spain, and this new project increases its overall capacity.
Company Background
Eurus Energy Holdings Corporation is a Japanese renewable energy developer, with shareholders including Toyota Tsusho Corporation. The company develops and operates wind power projects in Europe and has multiple facilities in Spain.
Project Location
The A Ruña II wind farm is located in the Galicia region of Spain. This area hosts numerous wind power facilities. The project’s completion allows Eurus Energy to continue expanding its renewable energy footprint in the region.