Main Works: Service Changes on Multiple Lines from August 1-28
As part of the renovation of the Atocha Cercanías station, a temporary operating plan will be implemented for several Cercanías lines from August 1 to August 28, 2026. This adjustment marks the final phase of the track layout optimization project.
The specific affected lines and adjustments are as follows:
- C-2 Line (Guadalajara-Chamartín-Atocha): Trains will not stop at Atocha, instead taking a detour via the loop line through Fuente de la Mora and Chamartín. Frequency will be reduced to every 20 minutes during peak hours and 30 minutes during off-peak hours.
- C-7 Line (Alcalá de Henares-Atocha-Príncipe Pío): Service will operate in sections. The Alcalá de Henares to Atocha section will run every 12 minutes during peak hours and 16 minutes off-peak; the Príncipe Pío to Nuevos Ministerios section will run every 30 minutes.
- C-8a/C-8b Lines (El Escorial/Cercedilla-Atocha): Trains originating from El Escorial and Cercedilla towards Atocha will have reduced frequencies of every 30 minutes during peak hours and 60 minutes off-peak.
- C-10 Line (Villalba-Príncipe Pío-Atocha-Chamartín): The line will be shortened to run between Villalba and Delicias stations, with a frequency of 30 minutes. The C-10 line platform entrance at Méndez Álvaro station will be closed during this period.
C-5 Line: Early Suspension and Alternative Transport
As a prelude to the major August construction, service on the C-5 line (Humanes-Móstoles El Soto) has been suspended between Villaverde Alto and Embajadores stations since July 22. Currently, trains are only operating between Humanes/Fuenlabrada and Villaverde Alto, and between Móstoles El Soto and Embajadores, maintaining a 10-minute frequency during the day. To bridge the suspended section, rail operator Renfe has arranged a replacement bus service between Villaverde Alto and Méndez Álvaro, with stops at Puente Alcocer, Orcasitas, and Doce de Octubre, running every 35 minutes. Passengers with a valid Cercanías ticket can also use regular routes of Madrid’s Municipal Transport Company (EMT) for free.
Sol Tunnel Closure: Weekend Disruptions for C-3 & C-4 Lines
Following the main construction period, the Sol tunnel will be closed between Atocha and Nuevos Ministerios stations for two weekends: August 29-30 and September 5-6. This will directly affect the operations of the C-3 and C-4 lines.
During this time, temporary terminal stations will be established:
- C-3/C-4 lines (from the direction of Parla) will terminate at Atocha.
- C-4 line (from the direction of Alcobendas/Colmenar Viejo) will terminate at Nuevos Ministerios.
Project Background and Long-Term Benefits
This series of works is part of the new track layout plan for Atocha station, a project with a total investment of approximately 56 million euros, partially funded by the EU’s ‘Next Generation EU’ recovery plan. The project aims to transform the current ‘4+3+3’ track configuration into a more efficient ‘4+4+2’ model. The infrastructure manager, Adif, has chosen to concentrate the works during the summer, a period of lower passenger traffic, to minimize the impact on public mobility.
Upon completion, the capacity of the Sol tunnel is expected to increase by up to 33% from October, particularly improving the efficiency and punctuality of the C-3 and C-4 lines during the morning peak hours (6:00 to 9:00). This is also the final major construction project scheduled to affect services through the Sol tunnel. Renfe will provide real-time information through customer service at stations, public announcements, social media, and its WhatsApp channel.