Construction Plan and Schedule
To address water leakage and pavement aging, Barcelona City Council will begin repairs on a section of the Ronda Litoral near Moll de la Fusta starting next Tuesday. The project is expected to last for two months, scheduled to be completed between October and December, with a total investment of approximately 740,000 euros.
To minimize traffic disruption, the construction will take place at night from Monday to Thursday, primarily between 23:00 and 05:30 the following morning. After each daily shift, workers will temporarily cover construction openings to restore normal traffic flow.
Traffic Diversion Routes
During the construction period, vehicles traveling in both the Besòs and Llobregat directions will need to detour, and some entrances and exits will be affected:
- Besòs direction: Vehicles must detour via Exit 21 and re-enter through Entrance 22.
- Llobregat direction: Vehicles must detour via Exit 22 and re-enter the ring road through Entrance 21.
- Maintenance Scope and Official Reminders
The project mainly involves injecting cement beneath the road base slabs to repair water seepage at the tunnel joints and improve road conditions, covering sections of the Colom and Moll de la Fusta tunnels built in different eras. Barcelona City Council reminds drivers to pay attention to traffic signs when passing through the area at night and to plan their routes in advance to avoid disruption.